2012 India blackouts
The July 2012 India blackout was the largest power outage in history , occurring as two separate events on 30 and 31 July 2012. The outage affected over 620 million people, about 9% of the world population or half of India's population, spread across 22 states in Northern, Eastern, and Northeast India. An estimated 32 gigawatts of generating capacity was taken offline in the outage.[5] An article in The Wall Street Journal stated that of the affected population, 320 million initially had power, while the rest of the affected population lacked direct access.
Electrical power was restored in the affected locations between 31 July and 1 August 2012.
Background
The Indian electrical infrastructure was generally considered unreliable. The northern grid had previously collapsed in 2001. An estimated 27% of power generated was lost in transmission or stolen, while peak supply fell short of demand by an average of 9%.The nation suffered from frequent power outages that could last as long as 10 hours. Further, about 25% of the population, about 300 million people, had no electricity at all. Projections suggested India remained decades away from having a sufficient energy supply.
In the summer of 2012, leading up to the failure, extreme heat had caused power use to reach record levels in New Delhi . Due to the late arrival of monsoons, agricultural areas in Punjab and Haryana drew increased power from the grid for running irrigation pumps to paddy fields. The late monsoon also meant that hydro power plants were generating less than their usual production.
Sequence of events
[edit]30 July
At 02:35 IST (21:05 UTC on 29 July), the 400 kV Bina-Gwalior line tripped. As this line fed into the Agra-Bareilly transmission section, the station also tripped, and power failures cascaded through the grid. All major power stations were shut down in the affected states, causing an estimated shortage of 32 GW. Officials described the failure as "the worst in a decade".
On the day of the collapse, Power Minister Sushil Kumar Shinde stated that the exact cause of the failure was unknown, but that at the time of the failure, electricity use was "above normal". He speculated that some states had attempted to draw more power than permitted due to the higher consumption. Spokesperson for Power Grid Corporation of India Limited (PGCIL) and the Northern Regional Load Dispatch Centre (NRLDC) stated that Uttar Pradesh, Punjaband Haryana were the states responsible for the overdraw. PGCIL's chairman also stated that electrical service was restored "at a record time".
A senior director for an Indian power company described the outage as "a fairly large breakdown that exposed major technical faults in India’s grid system. Something went terribly wrong which caused the backup safety systems to fail."
More than 300 million people, about 25% of India's population, were without power. Railways and some airports were shut down until 08:00. The busiest airport in North India, Delhi Airport, was able to remain open, because it switched to back-up power in 15 seconds. The outage caused "chaos" for Monday morning rush hour, as passenger trains were shut down and traffic signals were non-operational. Trains stalled for three to five hours.Several hospitals reported interruptions in health services,while others relied on back-up generators. Water treatment plants were shut down for several hours, and millions were unable to draw water from wells powered by electric pumps.
The Associated Chambers of Commerce and Industry of India stated that the blackout had "severely impacted" businesses, leaving many unable to operate.Oil refineries in Panipat, Mathura and Bhatinda continued operating because they have their own captive power stations within the refineries and do not depend on the grid.
It took 15 hours to restore 80% of service.
[edit]31 July
The system failed again at 13:02 IST (07:32 UTC), due to a relay problem near the Taj Mahal. As a result, power stations across the affected parts of India again went offline. NTPC Ltd. stopped 38% of its generation capacity. Over 600 million people (nearly half of India's population), in 22 out of 28 states in India, were without power.
More than 300 intercity passenger trains and commuter lines were shut down as a result of the power outage. The worst affected zones in the wake of the power grid's collapse were Northern, North Central, East Central, and East Coast railway zones, with parts of Eastern, South Eastern and West Central railway zones. The Delhi Metro suspended service on all six lines, and had to evacuate passengers from trains that stopped mid-journey, helped by the Delhi Disaster Management Authority.
About 200 miners were trapped underground in eastern India due to lifts failing, but officials later said they had all been rescued.
The National Disaster Management Authority (NDMA), not normally mandated to investigate blackouts, began to do so because of the threat to basic infrastructure facilities like railways, metro rail system, lifts in multi-storey buildings, and movement of vehicular traffic.
The following states were affected by the grid failure:
- states on the northern grid: Delhi, Haryana, Himachal Pradesh, Jammu & Kashmir, Punjab, Rajasthan, Uttar Pradesh, Uttarakhand
- states on the eastern grid: Bihar, Jharkhand, Orissa, West Bengal
- states on the northeast grid: Arunanchal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Sikkim
However, the following regions not affected at all:
- Narora and Simbhaoli in Uttar Pradesh
- parts of Delhi such as Badarpur
- areas served by Sterlite and Ib Thermal Power Station (most of western Orissa)
- most of the Kolkata municipal area (CESC system)
[edit]1 August
According to the officials of Uttar Pradesh Power Corporation Limited, the 400 kV double circuit line between Gwalior and Agra faced "dangerous overloading" on the evening of August 1 and could have triggered another power outage. The tripping was prevented when the powerpersons realised that the line load had reached 800 MW and scaled it down to 600 MW by cutting off the electricity to many parts that were fed by this line.
As of 2 August, Uttar Pradesh was being supplied about 7 GW power, while the demand was between 9 and 9.7 GW.
Prior disaster-proofing
Before the grid collapse, the private sector spent $29 billion to build their own independent power stations in order to provide reliable power to their factories. The 5 biggest consumers of electricity in India have private off-grid supplies. Indian companies have 35 GW of private off-grid generation capacity and plan to add another 33 GW to their off-grid capacity.
Some villages that were not connected to the grid were not affected, such as Meerwada, Madhya Pradesh which has a 14 kW solar power station built by US-based firm for $125,000.
[edit]Reactions
On the day of the collapse, Power Minister Sushil Kumar Shinde ordered a three-member panel to determine the reason for the failure and report on it in fifteen days. In response to criticism, he observed that India was not alone in suffering major power outages, as blackouts had also occurred in the United States and Brazil within the previous few years.
The Washington Post described the failure as adding urgency to Indian Prime Minister Manmohan Singh's plan for a US$400 billion overhaul of India's power grid. His plan calls for a further 76 gigawatts of generation by 2017, produced in part by nuclear power.
Rajiv Kumar, secretary general of the Federation of Indian Chambers of Commerce and Industry (FICCI) said, "One of the major reasons for the collapse of the power grid is the major gap between demand and supply. There is an urgent need to reform the power sector and bring about infrastructural improvements to meet the new challenges of the growing economy.
On 1 August 2012, newly appointed Power Minister Moodbidri Veerappa Moily stated, "First thing is to stabilize the grid and it has to sustain. For that we will work out a proper strategy." He declined to blame specific states, saying, "I don't want to start with the blame game.
Team Anna, the supporters of anti-corruption activist Anna Hazare, charged that this grid failure was a conspiracy to suppress the indefinite fast movement started on 25 July 2012 for the Jan Lokpal Bill and targeting Sharad Pawar.
Some technology sources and USAID proposed that another widespread outage could be prevented by integrated network of microgrids and distributed generation connected seamlessly with the main grid via a superior smart grid technology which includes automated fault detection, islanding and self-healing of the network.
[edit]Investigation
The three-member investigation committee consisted of S. C. Srivastava, A. Velayutham and A. S. Bakshi, and issued its report on 16 August 2012. It concluded that four factors were responsible for the two days of blackout:
- Weak inter-regional power transmission corridors due to multiple existing outages (both scheduled and forced)
- High Loading on 400 kV Bina-Gwalior-Agra link.
- Inadequate response by State Load Despatch Centers (SLDCs) to the instructions of Regional Load Despatch Centres (RLDCs) to reduce overdrawal by the Northern Region utilities and underdrawal/excess generation by the Western Region utilities.
- Loss of 400 kV Bina-Gwalior link due to mis-operation of its protection system.
The committee also offered a number of recommendations to prevent further failures, including an audit of the protection systems
BBC NEWS
Hundreds of millions without power in India
Hundreds of millions of people have been left without electricity in northern and eastern India after a massive power breakdown.
More than half the country was hit by the power cuts after three grids collapsed - one for a second day.
Hundreds of trains have come to a standstill and hospitals are running on backup generators.
The country's power minister has blamed the crisis on states drawing too much power from the national grid.
The breakdowns in the northern, eastern, and north-eastern grids mean around 600 m people have been affected in 20 of India's states.
HINDUSTAN TIMES
World's biggest blackout: 67 crore Indians without power
Punjab keasri
BLACK MONDAY...........
No comments:
Post a Comment